Gas Line Installation Cost in Sioux Falls, SD
LOW
AVERAGE
HIGH
What is the cost to Install Gas Lines in Sioux Falls, SD?
Knowing the gas line installation in Sioux Falls costs is important to being able to effectively plan and budget your project. While there are general nationwide numbers available, they usually do not include local factors that may impact the final price, which may include: local hourly labor wages, materials costs, as well as productivity rates. There may be certain Sioux Falls permits required by local state and city laws, which can raise the total cost as well.
Our numbers show that on average in 2014 total gas line installation Sioux Falls costs have been $369.20 to $427.52.
To breakdown that number by line the averages are $369.20 to $427.52 per line. This number includes the following:
- Average labor costs per hour in Sioux Falls which are typical of gas line installation projects.
- Materials and equipment costs necessary to install gas lines in Sioux Falls, SD, as well as any applicable delivery charges.
- Any applicable project preparation (necessary components, machinery and surface preparation) and cleanup fees.
- Sioux Falls permits required for gas line installation projects, which may also include inspection and building fees. Please contact Sioux Falls city government to inquire which permits may be necessary.
- Supply and material city sales taxes in Sioux Falls, 57103 area.
- Supply and material county and state sales taxes in Minnehaha county, South Dakota.
- Sioux Falls general contractor fees, if used for the project. Such fees usually add another 15% to the total. Using a general contractor is generally not required for Sioux Falls gas line installation projects.
Gas Line Installation Sioux Falls Projects - Cost Breakdown:
- $202.88 to $221.24 - typical hourly labor costs seen for gas line installation Sioux Falls projects in 2014.
- $138.72 to $150.22 - typical costs associated with Sioux Falls gas line installation projects in 2014. This figure may include mounting hardware, connectors and fittings, as required.
- $27.60 to $56.06 - tubing cutter, brazing kit, pipe wrenches and pipe cutting and threading costs, as well as any other necessary equipment and machinery.